Q: Not sure I understand how to process the data. I=E2=80=99m in eval mode.= I copied my data from my qb budget in csv format to the PL.csv file. I went to the budget complier and selected update =E2=80=9CUpdate Report=E2=80=9D.= I received an error message. It=E2=80=99s not clear to me how your worksheet gets the dat= a . Am I doing something wrong?
A: The Compiler imports the data from the PL.csv file when you click Update PL. This uses macros and macros must be enabled. An example PL.csv file is included in the download. You can initially test/try using the example PL.csv file. Simply download the software / extract all files to the same directory , open the Excel file compiler file that suits your excel version and then click Update PL on the Profit and Loss sheet. If macros are enabled the example data should be imported and displayed. You can then try with your own file.
Question and Answer Item 2058385 - Browse All Question and Answer Items